Restricting access to AGILE sprints

I want only a SCRUM Master to be able to add or remove items from a Sprint.

The KB article https://confluence.atlassian.com/agile067/jira-agile-administrator-s-guide/jira-agile-jira-configuration#JIRAAgile-JIRAConfiguration-Permissions says that to do that we need to removed the ability to edit or schedule issues form users.

The problem I have is that I want to allow developers to edit an issue but NOT add or remove it from a Sprint. Is this possible with the security schemes in Jira?

1 answer

This widget could not be displayed.

You can remove the Schedule Issue permission and keep the Edit Issue permission. Does that work?

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

216 views 3 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you