I use this code to get the original estimated workload in which time has been logged.

Then I get the sum of all on weekly basis. The problem I have is there are issues that are counted several times between 2 different weekdays. I guess it's because time has been logged into 1 issue several times in different weekdays. 

I want to exclude them and I don't know how. 

 

Calculated member 1
/*Return the original estimated based on the list of issues filtered */
Sum(
  Filter(
    /*All issues of the CurrentMember (e.g. Building) that started*/
    Descendants([Issue].CurrentMember, [Issue].[Issue]),
    [Measures].[Hours spent] > 0),
    /*We retrieve the workload planned for issues we started to work on*/
    ([Measures].[Original estimated hours],
    [Time].CurrentHierarchy.DefaultMember)
)
Calculated member 2
  Sum(
  PreviousPeriods([Time].CurrentHierarchy.DefaultMember),
([Measures].[member 1],[Issue Type].CurrentHierarchy.DefaultMember))

2 answers

This widget could not be displayed.

Hello @Lauma, what do you think ?

This widget could not be displayed.

Hello, Paul

Your assumption is correct - Filter with Hours spent will retrieve you an issue for each time period when any hours spent are logged.


If you would like to filter all issues with any hours spent then you could use Hours spent in a tuple with Time current hierarchy default member. In addition, you need to define in which Time period you would like your issues to appear to and any property could do a job.


For example, you could use Issue property ‘Issues created’ to retrieve issues on Time period when they were created and then apply an additional filter with hours spent and default time member to limit to only those issues with logged hours.

 

Please try this code:

Sum(
  Filter(
    /*All issues of the CurrentMember (e.g. Building) that started*/
    Descendants([Issue].CurrentMember, [Issue].[Issue]),
    DateInPeriod([Issue].CurrentMember.Get('Created at'),-- all issues at time when they were created
      [Time].CurrentHierarchyMember)
    AND
    ([Measures].[Hours spent],
    [Time].CurrentHierarchy.DefaultMember) > 0), -- additional filter limits to only thoses issues with hours spent
    /*We retrieve the workload planned for issues we started to work on*/
    ([Measures].[Original estimated hours],
    [Time].CurrentHierarchy.DefaultMember)
)

 

 Daina / support@eazybi.com

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

119 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you