I would like to be able to view all tasks and subtasks a the Project dashboard.

1) Is there a way to do that so I can see ALL tasks and subtasks listed with out having to click on each task to view the subtask? I would like a dashboard for each project where I can see all main tasks and subtasks listed.

2) If #1 above is possible, is there a way to manage/mark a task or subtask complete from the main dashboard?

3) Is there a way to make a task or subtask dependent upon another task? So, the initial task needs to be completed before the next dependent task can be started?

Thank you so much!!

1 answer

0 votes
Fadoua
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 14, 2017

Hi Leslie,

1-Create a filters for each of your projects (i.e. Tasks, subtasks) then add a gadget to your dashboard by selecting the filter you created

2-By clicking on the issue and then updating it.

3-Yes you can if you use the Bob Swift - update on Transition.

 

Best,