Portfolio target start and target end

Hi, 

On the documentation of Portfolio Server it describes the usage of target dates: https://confluence.atlassian.com/jiraportfolioserver/adding-target-dates-868977194.html

We're running v2.1.6 which (26th of Jan '17) is - as far as I know - the latest version. 

But we cannot find target dates anywhere. Is this documentation of some feature that has yet to be released? 

1 answer

0 votes

Hi! Target dates have just been released as part of Portfolio 2.2.0: https://confluence.atlassian.com/display/JIRAPortfolio/Portfolio+for+JIRA+2.2+Release+Notes 

After an upgrade, you should have full access to the new target schedule, and also the new capability to create multiple scenarios! 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

372 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you