Portfolio capacity question

I am evaluating Portfolio and have a question. I am in the Capacity / Story view grouping by person. I am seeing filled histograms (100% capacity utilization) for certain users, but I don't understand where the data is coming from. There are no issues assigned to that user that have estimates. Why is that user showing as 100% utilized?

1 answer

There is an unassigned issue on your sprint / data range.

When you have an unassigned item on your sprint/data range - it auto-assigns the item to the first user in your Team. If that member is filled up, it goes to the next person...and so on...

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

184 views 1 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you