Original estimate field missing on sub task?

I'm trying to add time estimates to sub tasks of stories that will then add up to the estimate for the story. I have time tracking on the sub tasks, so I can log time and it will adjust the remaining time but I cannot set an original time estimate.  Using the 'wheres my field?' option produces no results

 

 

2 answers

This widget could not be displayed.

Have you got the time-tracking field on the create/edit screens for the sub-tasks?

This widget could not be displayed.

This helps you get 90% of the way Remaining Estimate Time Tracking and Stories. How to Apply Time to Subtasks during Planning

Then you need to add the time tracking field on the create/edit screen. The easy way to do this is create a sub task in your user story. Then select configure field tab (top right), and select where is my field. This will then give you a link in order for you to be able to enable the time-tracking field on the sub task edit screen. You will not be able to estimate in story points and add the original time estimate. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

168 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you