Milestones in Jira Gantt

Corinna Führing December 17, 2015

Does anybody know if it is better to create a Milestone in JIRA using an extra Issue Type or just putting estimated Time in 0 ....?for Gantt Chart Plugin

1 answer

0 votes
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 23, 2016

Create a separate issue and set Gantt-option "milestone": doing this, you can link multiple issues to this milestone e.g. using "finsh-start" dependency link type. If you shift one or more of this issues without having any buffer later, then the milestone becomes "red" indicating any breaching.