Kanban board - Task over 2 weeks

Hi there,

Is there a way to set up a task to go over 2 weeks in a Kanban board. We have a swimlane for each of our sprints.

So we want to have the task appear in both swimlane (sprints). Currently it just appears in the latest dates Swimlane (sprint).

 

Cheers!

1 answer

This widget could not be displayed.

No, an issue should only appear on a board once, so it will land in the first swimlane it matches and not be repeated.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted 3 hours ago in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

16 views 0 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you