Jira Portfolio 2.0 - How do I get my tickets in Portfolio 2.0 to show up in a sprint in the Project?

I brought my tickets/epics into Portfolio 2.0 - I want the tickets to show up in the project under the correct Sprint that Portfolio 2.0 created.

 

How can this happen?

1 answer

This widget could not be displayed.

Hey Kyle,

Firstly is the relevant board associated with a team in your plan?

On the team tab make sure you have a team associated with your board as an issue source (via the drop-down under the team name).
This will make sure that your sprint dates, sprint issue assignment and sprint names are recognised in your plan. This will also allow you to assign issues to sprints in JIRA from Portfolio which can be done in two ways:
  1. Select the specific sprint for the issue using the sprint column
  2. After your plan calculates a schedule for your sprints you can make sure they are integrated with your JIRA board. Click the sprint name and assign the calculated issues to the sprint.
You can see this process in action in this part of our demo video: https://youtu.be/LexaHkZls3g?t=976
Let me know you you have any further questions.
Cheers,
Rhys

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

201 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you