Jira Core FIx/Version

Daniele Margaroli May 13, 2019

Hi,

i'm using Jira Core with a Business Project. 

I have several completed issues that are associated with a version. In the project settings I released the version but all those issues were migrated to the next version. How can I keep the completed issues to the closed version?

Thanks,Daniele

1 answer

1 accepted

1 vote
Answer accepted
Ramarao Gaggara {Appfire}
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 13, 2019

Hi @Daniele Margaroli

 

One of below 2 fields might help you to set the version.

And to add the version for all issues at once, you can do this by performing a bulk operation. Please refer below link to know more details about how to do bulk operation.

https://confluence.atlassian.com/jiracoreserver073/editing-multiple-issues-at-the-same-time-861257342.html

 

Thanks!

RamaRao

Daniele Margaroli May 13, 2019

Hi @Ramarao Gaggara {Appfire}

I fix theproblem. The issues were moved to the next release because the field "Resolution" remained "unresolved".

I solved by adding the field change to the transaction.

Now when I close the release the closed issues remain associated with the same release

 

Thanks,

Daniele