Does anyone know how Jira decides if a resource is booked for too much work? I understand that more points means more of their effort is required, but doesn't that mean that Jira then assumes that a certain amount of points always takes a certain amount of days to accomplish? Does it take into account past sprints? I am using points to measure the velocity of my team, and also percentage as an indicator for how much work each developer is tackling. I am trying to figure out the resource usage is calculated on the back end - any ideas?
Thank you,
Yuta
Hi @Yuta Nagano ,
It's a good question, as the calculations for obtaining velocity are not intuitive.
First, let me clarify that Jira does not assume any conversions from Story Points into time.
The Velocity Chart is calculated by taking the average of the total completed estimates over the last several sprints.
More information on how to understand the Velocity Chart:
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/
Hope it helps.
I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.