Issues completed outside of this sprint

The issue that appears in a Sprint report under this category has the same Sprint number in a Sprint field as all other issues. How it was determined that it was completed outside of the Sprint? 

1 answer

1 accepted

These are the issues that were not in the sprint but were completed during the sprint or issues which were completed before the sprint started or after it ended.

Issue was moved to status Done on June 16. I completed sprint today. So it doesn't add up.

You are right - I was fooled be looking at our own sprints, but this was just a coincidence. I've done some digging and edited my answer.

We have several occasions where stories were marked as done before the sprint was actually started - they all show up in "Issues completed outside of this sprint".

Thanks, I think this makes sense.

I have no idea why this is not in the official docs - this same question has been asked before. Please accept the answer so this one is closed. Thanks!

I accepted your answer. But in fact in our case it was a bit more complicated. We removed this issue from the active sprint, because of some misunderstanding. Then it was put in status Done and moved back when sprint was still active. And now JIRA report shows is as completed outside of the sprint.

Hi Petar,

 

Is there a way to fix this issue, if you want the issue to be part of the sprint and part of the chart, can this be fixed by modifying data in the database? Or is there a way to do it in the UI?

 

Thanks

Barry

I have an issue with this as well. Issues completed outside of sprint are showing up in my gray commitment bar chart on the velocity chart. This is creating inflated commitments for some of my teams. It seems that if someone finishes a story in a 'future sprint' before that sprint starts, the story is counted as a commitment in the velocity chart. I don't think this should be the case. Is this an known issue? Is there a workaround to it?

Here is my sprint report - 

image2016-12-4 22:53:27.png

 

Here is the velocity chart for the same sprint

image2016-12-4 22:55:10.png

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Fadoua M. Boualem
Published Monday in Trello

Using Trello to manage events

As a Jira power user, I was at first doubtful that Trello could benefit my workflow. Jira already uses boards (ones you can customize!), so why would I even need to use Trello?! In this post you will...

516 views 8 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you