Is there an "In Progress" point on the burndown chart?

I would like to see a point marking when a story is set to "In Progress" on the burn down chart. It would make it easier to see if a specific story was estimated correctly or took too long to complete. Is there a functionality like this already built in?

1 answer

1 vote

JIRA has a built in field called workratio which compares the original estimate vs time spent. You could create a filter saying:

Project = xxx And workratio > 100

This would give you all issues where time spent was more than the original issues. 100 stands for 100%, btw.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

242 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you