Is there a patch to make the wording for linked sub-tasks correct?

confusion.png

 

If I have an issue (#68) and 'link' it to a parent task (#68), the wording to describe the relationship between the two is exactly the same, whether I'm viewing the parent or child task. It says they are BOTH sub-tasks.

Is there a patch to fix this? I need the child issue to say "is a sub task of" the parent and the parent issue to say "is a parent of" the child. There needs to be two messages. The other linking options work correctly, but not this one.

 

2 answers

1 accepted

2 votes
Chris Fuller Atlassian Team Aug 09, 2016

This text is something that the administrator can edit:

ViewIssueLinkTypes.png

EditIssueLink.png

 

Thank you! Fantastic.

Suggest an answer

Log in or Join to answer
Community showcase
Emilee Spencer
Published 8 hours ago in Marketplace Apps

Marketplace Spotlight: DeepAffects

Hello Atlassian Community! My name is Emilee, and I’m a Product Marketing Manager for the Marketplace team. Starting with this post, I'm kicking off a monthly series of Spotlights to highlight Ma...

30 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot