Is it possible to create/convert a new sub-task with a new prefix?

Mohin Uddin November 8, 2015

Hi Expert,
Is it possible to  create/convert a new sub-task with a new prefix?
Could you please inform me regarding this issue?


Thanks
Mohin 

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 8, 2015

What do you mean by "new prefix"? 

If you mean the project part of the key, then no.  A subtask belongs to a project (because it belongs to a parent issue) and hence must take the project key.

0 votes
Mohin Uddin November 8, 2015

Thanks Nic Brough.