Including Future Sprint in an Active Sprint's Scrum Board

Austin Equitz February 28, 2017

Is there a way to include a future sprint's backlog in an active sprint's scrum board? The purpose of this would be to allow users to drag tasks from future sprints into the current one if they complete all assigned tasks in the current sprint.

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2017

You can have multiple sprints planned in advance and see them all, including the active sprint, in the backlog view. You can then move stories from the future sprint to the active sprint, although that will change the sprint scope.

You cannot see the future sprints in the "Active Sprint" view though. Hope that explains!