This question is in reference to Atlassian Documentation: Configuring Estimation and Tracking
I have enabled Time tracking to "Remaining Estimate and Time Spent" but I don't see the burndown.
I have tasks in sprint that are completed but do not see the remaining values reducing.
Do you have any values inside the Original Estimate field and is there any work logged for the issues ?
When you use the "Remaining Estimate and Time Spent" option the burn-down is not based on the status of the user story (i.e. todo/done), but it's calculated based on the values of those two fields.
I have Subtasks under User Stories and Each of the tasks are given Original Estimates. And when work is logged the team updates the Remaining Estimate for the task and the team sets the Remaining Estimate to Zero when the task is done. This should ideally show me a burndown on the Remaining Values but I see a flat Red line
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.