I have enabled Time tracking to "Remaining Estimate and Time Spent" but I dont see the burndown

This question is in reference to Atlassian Documentation: Configuring Estimation and Tracking

I have enabled Time tracking to "Remaining Estimate and Time Spent" but I don't see the burndown.

I have tasks in sprint that are completed  but do not see the remaining values reducing.

1 answer

Do you have any values inside the Original Estimate field and is there any work logged for the issues ?

When you use the "Remaining Estimate and Time Spent" option the burn-down is not based on the status of the user story (i.e. todo/done), but it's calculated based on the values of those two fields.

I have Subtasks under User Stories and Each of the tasks are given Original Estimates. And when work is logged the team updates the Remaining Estimate for the task and the team sets the Remaining Estimate to Zero when the task is done. This should ideally show me a burndown on the Remaining Values but I see a flat Red line

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

222 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you