How to hide only Time Spent Field and keep Original and Remaining Estimate

Tamil January 17, 2021

Hi ,

We are using Tempo for Log time and we also have the Jira Field Time Tracking(Time Spent,Remaining Estimate,Original Estimate).

 

The Estimation fields are useful but for time spent we want to use only Tempo.

Is there any way to make read-only of field "Time Spent" only and keeping Original and Remaining Estimate. 

 

Note: I have eliminated "Log work" from Issue View--> More. In issue screens, we are using Time Tracking field. We want to keep only Original and Remaining Estimate and disable Time Spent

 

 

1 answer

1 accepted

1 vote
Answer accepted
Tansu Akdeniz
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 18, 2021

Hi @Tamil 

If you only want to use Tempo for worklogs, follow the steps to disable default Jira worklog.  Otherwise there will be two different alternatives for users.

Best

Tamil January 20, 2021

@Tansu Akdeniz  I have disabled the modules already. In addition we have Log work in Transitions which have Time Spent field. I eliminated Log work field from Transitions.

Suggest an answer

Log in or Sign up to answer