Scenario - Issue is logged in one sprint and developers gets the task in another sprint to fix bugs. If tester log issue in one sprint na dfix in another sprint. Can I attach two sprint against a bug? If yes how?
If No, then please tell me how to handle such scenarios in JIRA for agile projects?
You could include it in different sprints on different boards. The complexity comes in that it can look odd if someone does something in sprint-1 (most importantly, marks it "done") and the board for sprint-2 is configured different and doesn't see the change the same way the other sprint does.
A board won't let you put the same issue in two of its own sprints though, that would be nonsense.