How to filter on Epics in a Kanban board

Hi,

We are changing from a scrum board oc a kanban board. What I miss in Kanban is the Plan vew where I can filter my issues with for example epics. I Kanban it looks as the to do list is a non filter and a non hierchy list with epics, stories and tasks in a long list.

Is there a solution to this problem?

1 answer

Unfortunately that's one of the capabilities you lose between the two boards.

You could add Quick filters for the EPICs on your Kanban board, but it's not going to be as pretty.

You could (as we did for awhile) continue to use your scrum board for planning with one sprint that never closes.

Just a few ideas/thoughts...

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

82 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you