Our team uses JIRA 6.4.2 with the standard JIRA software workflows. Now we'd like to use JIRA Core, but when I try to create new project I still see only standard projects (Simple issue tracking, JIRA default Scheme and others) 

How can I enable JIRA Core functionality and can we use JIRA Core and JIRA Software together?  

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 12, 2015

JIRA Core really is the core of JIRA.  There is nothing to "enable" - you just upgrade from 6.4.2 to 7.x and that's it, you have JIRA Core, with all your data.

JIRA Software can be added later, but if you already use the Agile add-on, I'd strongly recommend upgrading from JIRA 6 + Agile to JIRA Software.

Elena Kolpakova November 12, 2015

Thanks a lot! This information was not clear from JIRA Core description.