How can i get a JIRA report with issue time tracking by sprint?

In the case of an issue or a subtask not being completed in a single sprint and i have to reestimate the time, how can i have a report of logged and estimated time spent by sprint?

Thank you in advance

1 answer

1 accepted

1 vote
Accepted answer

Hi André Manique,

You add the column Original Estimate and Remaining Estimate.

image2016-7-4 11:12:8.png

And to the JQL you will use:

sprint = "name_of_sprint" and status = Unresolved

So you can see the issues unresolved at a specific sprint.

I think you looking for that.

Regards,
Lameck. 


Olá André,

Acredito que você seja brasileiro, então, resolvi colocar o texto em português também. 

Você pode adicionar as colunas de estimativa para visualizar os valores na tabela, e utilizar o seguinte JQL para visualizar apenas as atividades não resolvidas do Sprint:

sprint = "name_of_sprint" and status = Unresolved

Abraço,
Lameck. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

221 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you