How can i get a JIRA report with issue time tracking by sprint?

In the case of an issue or a subtask not being completed in a single sprint and i have to reestimate the time, how can i have a report of logged and estimated time spent by sprint?

Thank you in advance

1 answer

1 accepted

Hi André Manique,

You add the column Original Estimate and Remaining Estimate.

image2016-7-4 11:12:8.png

And to the JQL you will use:

sprint = "name_of_sprint" and status = Unresolved

So you can see the issues unresolved at a specific sprint.

I think you looking for that.

Regards,
Lameck. 


Olá André,

Acredito que você seja brasileiro, então, resolvi colocar o texto em português também. 

Você pode adicionar as colunas de estimativa para visualizar os valores na tabela, e utilizar o seguinte JQL para visualizar apenas as atividades não resolvidas do Sprint:

sprint = "name_of_sprint" and status = Unresolved

Abraço,
Lameck. 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

632 views 3 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you