How can I change the Sprint report graph to show Story Points instead of hours. I can't find any option that would allow me to do it.

This question is in reference to Atlassian Documentation: Viewing the Sprint Report

Ask your question here...

1 answer

1 accepted

1 vote

Go to board configuration and change the estimation statistic to Story Points.


Estimation Statistic was already set to "Story Points", however Time Tracking is set to:

"Remaining Estimate and Time Spent

Track time against issues using JIRA's Remaining Estimate and Time Spent fields." which is probably why the report displays hours. 

Suggest an answer

Log in or Join to answer
Community showcase
Alexey Matveev
Published Saturday in Jira

How to run Jira in a docker container

Everything below is tested on Ubuntu 17.10. I prefer to use Jira in a docker container because: 1. I can install Jira with a couple of commands. 2. I can start and stop Jira just by starting and s...

435 views 6 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot