I want to Apply a rule for changing the status from an Item, it has to be connected to a Sprint to go from "To Do" to the next status.
The best way to do this is to add a "validator" to the workflow transition from To-do to the next status. A simple "sprint is not empty" one will do it. (You could also do it with a "condition", but that would hide the transition from people and there's no way to tell them on-screen what is missing. A validator will tell them that the sprint is missing)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.