Hourly scheduling doesn't appear to work properly in Portfolio.

I've got a portfolio plan that is Kanban and is counting in hours.

I've got a team with one user, who has a weekly working hours of 40, and the plan is set to have 8 hours a day, 5 days a week.

I've got a number of 1 hour stories, which are scheduled today.

However, portfolio is only putting 3 hours of work in today, and punting the rest of the 1 hour stories to tomorrow.

Why doesn't portfolio schedule 8 hours of work today? 

I've made sure my user isn't in any other teams or plans, and I've tried playing with the number of hours that that user works and the number of hours in a day, but I can't seem to get a sensible schedule to pop out.

 

Help! Thanks smile.

Joe

1 answer

This widget could not be displayed.

Hey Joe, this doesn't sound right indeed, but hard to answer/analyze without an export of the actual plan - could you reach out via support.atlassian.com with a plan export (Plan > Export...). There is an option to "Render data anonymous" so there is nothing sensitive sent anywhere. Like this our support team can get back with a specific answer. Thanks! Martin Suntinger, Product Manager, Portfolio for JIRA

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

169 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you