I have an issue about the timesheet approval funtion. In the below case:

  • on the system, i set the timesheet approval funtion is 1 week 1 times.
  • David who he joined to 3 projects(3 PM of 3 projects: Mark, Jay, Susan) who he got approval his timesheet in the current week.
  • But Mark or Jay or Susan, they can approve David's timesheet only one times, Althought, the remainning PMs does not review David's timesheet. As his all timesheet in 3 projects are approved.

However, my expect: if Mark approve David's timesheet and the time is only approved for the period time which David's logged for Mark's project.

Pls, help me in this case or suggest a best method to process my case. Thank you very much!

1 answer

is there have anyone can help me? Pls Help me, thank!

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

77 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you