Epic report - Some issues are considered as incomplete even though marked as Done

 

Some observation:

This is happening after I defined new status (Resolved) in the category Done.

Only resolved issues are being considered as complete issues in report.

Let me know what I am missing here. Epic reports are showing wrong data/reports/numbers

Here are some snapshots :

incomplete issues.png

Velocity reports are also showing wrong

velocity.png

 

 

2 answers

1 accepted

This widget could not be displayed.

All the statuses that you consider "DONE" need to map to the "Done" column.  The status or resolution of your issues is irrelevant  - it's the mapping of those statuses to the done column.  (There is only one done Column on your board.)

Yeah..We should check the columns in the when Sprint is viewed. Irrespective of the statuses of issues, for Sprint completion, it only checks the Done column. And you must have only one 'Done' column

This widget could not be displayed.

It really helped - Thanks a lot for quick reply @Andrea Carl

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

113 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you