Hi,
I would like to use the same calculated fields defined in the system, but would like to modify the formula.
Currently, the current field, C = A * B. It applies to certain issues but has Global context.
I have my project's field configuration scheme, and I can edit the formula in my field configuration to be C = A + B. However, the calculated value still results in C = A * B.
Is there a way to do that?
Thanks.
Hi Steve,
Yes, we are using the Misc Custom Fields add-on.
Hmm, yeah, I don't think that worked.
I tried setting another project-specific context within the custom field configuration, but there's only one place to edit the formula, so it doesn't look like you can set a formula per context.
I did also modify the formula within the field configuration scheme, but that didn't work either.
Thanks for the help.
If you're using Misc Calculated Fields add-on (you don't indicate which add-on you're using to achieve this), you cannot use Field Configurations for formulas.
Have you considered setting different project-specific contexts within the Custom Field Configuration? I've never tried this before.