When I have created a portfolio with a plan on what should be worked on - how can I then convert that into a project with tasks that I can then complete together with my team?
I understand I can import tasks into a portfolio, but I'm interested in the other way around.
Hey Patrick, the other way around you can do "Create and link issues". This is available in the dropdown of each work item, if you trigger it on an epic or an initiative, you can then create everything underneath in bulk.
image2015-12-2 10:17:48.png
If you are using sprints, there is also a second way to do it, by clicking the sprints label in the stories view and choosing "Create issues in project"
image2015-12-2 10:19:11.png
In both cases it will open a dialog allowing you to choose the issue type and some more options of what you want to set on the issues
This essentially after creating like this, you'll have the same linking as when importing existing issues into the plan, so you can push changes onto these issues by using "Plan > apply updates to projects", and pull in plan updates and tick off completed work by doing Plan > Update from date (which also sets a new start date for the schedule and plans forward from there)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.