No.

The point of a sub-task is that it is part of the parent task.  So if the parent task is pulled into a sprint, it's nonsense to try to put its parts into another sprint.   If you find yourself wanting to do this, then you need to split up your parent tasks better.

This widget could not be displayed.

Thanks for confirming.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

278 views 1 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you