Can JIRA 3.13 be upgraded directly to JIRA 7, or are intermediate version upgrades still required?

Christopher Gores October 14, 2015
 

1 answer

2 votes
J. Caldwell
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 14, 2015

You will need to do intermediate upgrades. The jump from 3.x to 4.x is a big one and that's the one that you have to step up to if you want to go to 5.x/6.x first. 

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 14, 2015

I'd go 3.13 to 4.4.latest, and I think I'd probably go to 5.2 or 6.0 before 7 as well.

Dave C
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 14, 2015

As of JIRA 5 we dropped upgrade tasks for versions less than 4.0, so as everyone else says you have to go to 4.4.5 first. No need to go through the other major versions, all the upgrade tasks are still in the later versions. 3.13 > 4.4.5 > 7.0 :)