Can 'Issues In Epic' display time spent on a ticket

Hi

When we use 'Sub Tasks' on a ticket the time spent on the ticket is displayed next to it (as shown in the attached picture).

Is it possible to get this time spent feature to show next to all issues that are under the heading of 'Issues in Epic' ?

Kind regards

Adam

1 answer

For subtasks, this can be configured in Administration / Advanced Settings, by changing the columns in the jira.table.cols.subtasks property.

However, Epics are from the JIRA Agile plugin, before JIRA 7 at least, so you won't find a similar option there for Epics. I had a look at the documentation and at the modules of the Agile plugin, and it doesn't look like that option exists.

If you're using JIRA 7, I suggest you take a look anyway in the advanced config and in the system plugin modules. But I'm not hopeful.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Fadoua M. Boualem
Published yesterday in Trello

Using Trello to manage events

As a Jira power user, I was at first doubtful that Trello could benefit my workflow. Jira already uses boards (ones you can customize!), so why would I even need to use Trello?! In this post you will...

425 views 5 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you