Can I change Burndown chart after changing the storypoint

Ihor June 22, 2018

Hi there,

can I somehow change the burndown chart if the storypoint was changed. If I start sprint, Burndownchart take the storypoints and calculate it if the Issue is closed. Now we have one Issue witch was estimated with 8 Points and after done was changed to 2 Points. So burndown chart is still showing us 8 Points and not 2. Is there any way to change it?

image.pngimage.png

1 answer

0 votes
Mark Markov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 22, 2018

Hello @Ihor

After issue resolved (have resolution), changes in storypoints no loger affects the scope.

If you want to change storypoints in resolved issue and see changes in scope, you need reopen issue(any unresolved status), change storypoints and close it again.

Ihor June 25, 2018

@Mark Markov Thanks for fast answer. I have reopen the issue and changed the storypoints, then to done, but it not helps :-(

Burndown chart is still the same.