Automatically populate due date from the original estimate

Rahul Aich [Nagra]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 19, 2016

Hi All

I want to automatically populate the Due Date field directly from the original estimate.

Say, if original estimate is 5 days, then due date should be set to current date + 5 days.

Isit possible to configure something like this?

Rahul

2 answers

0 votes
Swati Kahol
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 2, 2020

Hey @Rahul Aich [Nagra] 

We have recently published a kb article to add Orginal estimate to a date field using Automation for Jira. Hope this helps :)

https://confluence.atlassian.com/cloud/automate-due-date-of-an-issue-from-original-estimate-1021245282.html

Thanks
Swati

0 votes
Boris Georgiev _Appfire_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 19, 2016

Here're some ideas:

  • write a scripted post-function (JJUpin or Script Runner) that updates the issue 
  • write a scripted issue Listener that does this - again using one of the scripting add-ons

 