By default, the current subtask fields show in the parent issue
I want to also display the due date, but I don't want to force every other project to do this.
Hi David,
the sub-task panel is very difficult to configure out of the box. You can show only certain fields - only the so-called system fields and the configuration is one for the whole system, it cannot be changed by projects.
The only solution is to use this plug-in Issue Matrix. Basically you should create a custom field of type Issue Matrix, select sub-task mode and configure which fields you want to show as columns.
If you have any questions let me know.
Cheers,
Peter T
As a project administrator, you can't do this.
As a system administrator, it's really easy to do it globally, you can add any system or custom field to the display by adding them to the jira.table.cols.subtasks property in admin -> general config ->advanced
But it is global, not by project. To limit it by project, you need code