Adding a stage to a release stream in Jira Portfolio

In JIRA Portfolio I'd like to add a beta release to a Release.  In summary, we have a number of epics that are being rolled out in a release, but we want to do an internal roll out before it goes out to the public.  What is the best way to add this to the schedule stream in JIRA Portfolio?

1 answer

0 vote

Hi Warren, There is no dedicated concept for a sort of beta release - I'd recommend representing it simply as a "normal" release within a stream. The more interesting question will be: As for the efforts you have estimated on your backlog, do you need them done until the internal rollout, or the public release? Personally I focus the releases in Portfolio on the dates we need to get the work scheduled for, so that might actually be the beta date, leaving some leeway, or some dedicated work items to be scheduled between beta and the public release date. 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published yesterday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

59 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you