Add ready for testing status stories as completed issues in Velocity charts

Vasco Guimaraes August 15, 2016

I've been chasing for this answer in your forum and online but I couldn't find it yet and it would be very important for me. Can you please help me?

I want to have the ready for testing status counted as completed issues in my sprints velocity charts. Is this possible to do in JIRA?

At the moment, the Ready for testing stories do not count as completed issues during the sprint so when I go to Reports - Velocity Chart it shows only the the resolved or closed status stories. Can you please help me if this is possible and how?

Thank you in advance for your help

1 answer

2 votes
Tarun Sapra
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 15, 2016

The "Ready for testing" status should be the "Right-most" column on your scrum board and when the issue is moved to "ready for testing" the resolution should be set.