A 'subtask' option already exists, but it doesn't appear when I create an issue. Why?

Mik Scheper January 5, 2017

This page says to select ⚙→Issue Types→Sub-Tasks to enable subtasks, but when I go to ⚙→Issue Types, 'Subtasks' are already listed. Nevertheless, when I create an issue, 'subtask' is not an option. Why?

1 answer

2 votes
Volodymyr Krupach
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 5, 2017

Sub-task can be created only in context of parent issue. So select some issue and then create a subtask from its menu:

image2017-1-6 9:49:0.png

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 6, 2017

If it's not there, then check that the project's issue type scheme has at least one sub-task type in it.