Is there a method/report available to filter, Billable work hours down to 3 levels; Project wise, User wise, Task to monitor Planned vs Actual?

 

Ex-

Project name

     User1

          Task 1

          Task2

     User2

          Task1

 

thanks, 

Randika

1 answer

1 accepted

0 votes
Answer accepted
carolyn french
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 9, 2022

Hi @Randika Palipane ,

You can group by Epic in Planned vs Actual Report, however, I think the view you are looking for is actually in the Logged Time Report. You can add the columns Planned time, Billable time, and Logged time to your report, and then group by those 3 parameters- Project, User, Task.

You can click the top of the Billable column to sort to see the ones with billable time at the top. Alternatively, if you are using Billable Accounts, then you can filter by those Accounts.

Here's what it could look like. Make sure you enable the extra columns to show up:

Tempo Report - Logged Time Report.png

Randika Palipane March 9, 2022

Hi @carolyn french

Thank you very much! this helps my purpose. 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events