Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,457,698
Community Members
 
Community Events
176
Community Groups

Multiple Scrum Board per Project

Our company recently upgraded to 7.13 from release 6.x . As project administrator I was able to open multiple sprints in the same project as we have two teams that work off of the same project.

 

Today I open a sprint for one team, but the other team's sprint is grayed out saying:

"Can be planned but not started until the completion of above active sprint"

3 answers

1 accepted

2 votes
Answer accepted

Yes, you can usually only have one sprint on a board at once.

If you are an admin, you can go to "labs" and enable "parallel sprints" to get many sprints to run at the same time, but it is experimental.

FWIW, we've been working with clients using parallel sprints and also using the feature internally for years and have never seen an issue with it. I wouldn't be afraid to enable it.

As I say, we have been using this feature for a while.  Yes, it is unfortunate that some of the features of rolling uncompleted items to the next sprint, and getting sprint reports accurately from JIRA is a pain, but the later we have worked around with add-ons.

 

Thanks for the feedback.

Our admin team enabled the feature and all is as it was.  Thanks for the response.

I don't see this in my "Personal Settings" -> "Labs". Is this still available for you? If so, can you post a screenshot?

jira settings > products > jira software configuration > Parallel Sprints

Not successful in Company Managed project(formal classic): jira settings > products > jira software configuration > Parallel Sprints 

This feature option doesn't provide me dual sprint functionality. 

 

Are there any other steps to be followed to make it work separately?

 

 

Any help here? Thanks!

Hi All,

 

We have multiple teams working on the same Product Backlog. So in Classic Jira we had multiple scrum boards (one board for each team). However, I could not find the same functionality in Next Gen Jira. Please help.

Next-gen does not support this yet, I am sorry.

Suggest an answer

Log in or Sign up to answer