You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I have a team that has been utilizing the "due date" field in jira. However, they have been manually assigning the due date in active sprints to be the last day of the sprint. I'm hoping I can configure it so that when a sprint is started, all tickets in the sprint that don't already have a value in the "due date" field have an auto-assigned due date of the last day of the sprint
Hi @Akwo Akwo
Do you have automation for Jira installed on your instance? If so, you could create a rule triggered on Sprint Started to set the field. Please check with your site admin to learn if the addon is installed.
To learn more about automation rules, please take a look at these sources and examples:
Kind regards,
Bill
I don't have automation install on my instance. I do have Script Runner which I believe will be good. Am educating myself with Script Runner.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for that information. I have not used ScriptRunner for many years, so let's see what other community members can suggest for using that addon.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.