I'm able to see Sub-Tasks as part of the main Board page.
I've even added all issue types for the scheme, and the sub-tasks still don't display under the task.
I was expecting that the sub-tasks would appear under the Task it is was created from, but it isn't appearing until the task's tile.
The sub-task doesn't appear anywhere else on the board, either.
I don't know if something is really wrong, because searching for the issue number in this field:
...it can't find the issue either (meaning I have to manually go looking for it, or search in from the side bar).
Any help you could offer would be great.
Thanks in advance.
Z.
Hello Zaac,
Sorry to hear you are facing this problem.
Indeed, the Business board use simpler functionalities than the default software boards, and it does not display sub-tasks as you mentioned.
I completely agree with you that this would be a useful feature to have, so we reported the following feature request to get it implemented:
- Business boards show sub-tasks
Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.
Let me know if you have any questions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.