I am trying to execute multiple run parallel but configured Jobs in one plan are being executed sequentially. I have configured it for parallel run according to the link https://confluence.atlassian.com/bamboo/configuring-concurrent-builds-289277193.html. But not worked.
If I am doing anything wrong, please give the solution.
Thanks.
In addition to enabling "Concurrent Builds", and setting "Default number of concurrent builds allowed" to a number > 1, there should also be multiple agents be available to run the build.
If you have configured concurrent builds, but there's only one agent available, everything will still be executed sequentially.
No can do
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What are you trying to run n parallel? Plans, Jobs, Stages? Tasks in a Stage will run in parallel by default
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
not Tasks but Jobs are execute in parallel.
Bamboo_Workflow.png
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oops, you're correct. A picture says more then a 1000 words