Hi All,
Does Bamboo allow to run on the same agent a build plan for a project and deploy (existing artefacts from previous builds) for the same project concurrently?
Considering build agent has enough horse power - is there any way to achieve this?
I don't want to use/install/etc. a second agent while I've got good hardware on existing one.
Reason: build process takes long time (including tests) while deployment is quick.
At the moment I have to wait until build finishes (deployment task is delayed) ...
Thanks,
Constantin
You can install multiple agents on the same server but one agent can only run one build at any one time.
Tahnks Timothy,
I installed the 2-nd instance of Bamboo agent in a separate directory.
Regards,
Constantin