The commit isolation functionality in Bamboo is really useful for highlighting which check in has caused a break.

One problem we've found is that upon re-enabling a disabled plan, the runs continue for all checkouts that occurred whilst the plan was disabled. Is there a way to prevent this and to tell it to only start running for each commit since a certain revision?

Thanks.

1 answer

1 vote
Marcin Gardias
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 21, 2014

> Is there a way to prevent this?

Not automatically.

Doing this the hard (manual) way, you can disable commit isolation, enable the plan, run it once and then reenable commit isolation.