Can I run builds one after another even if the parent plan (plan before) fails

I have a number of builds that I need to run in sequence. I am not bothered if the plan before (parent build) fails or not. The only thing I am interested in getting all the build in a plan to run one after another with only one agent.

Currently the first build runs but when it fails, it does not trigger off the other builds.

This is a big thing for us as these plans means extra hours of work because we are unable to run all the plans.

1 answer

Hi Usman,

This is not configurable at the moment but you can have a look at this feature request https://jira.atlassian.com/browse/BAM-6434

Suggest an answer

Log in or Join to answer
Community showcase
Renan Battaglin
Published May 18, 2017 in Bamboo

FAQ: How to Upgrade Bamboo Server

Bamboo 5.9 will no longer be supported after June 12, 2017. What does this mean? As part of our End of Life policy, Atlassian supports major versions for two years after the first major iteratio...

1,066 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot