Hello, I would like to set that he does not necessarily change the agent between two stages. Or in one stage 2 jobs in parallel and the 3 job last but on a certain server on which a certain job was running.
I'm seeing similar behavior, and have searched high and low through the docs. Nothing I've seen makes reference to this.
I have multiple stages. They are indeed run sequentially, but a different agent seems to run each stage. This is neither advertised nor desired behavior. The problem is some of the tools I use generate absolute paths. Since each agent operates out of a different temp path, when using different agents, absolute paths generated in one stage are invalid for another.
How do I correct this problem without adding more 'requirements'?