how do I set original estimate

remainingg is set as optional but nothing is going into original estimate

1 answer

1 accepted

2 votes
Answer accepted
Ramiro Pointis
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2013

If I remeber correctly you have the option to add Original Estimate in the Create Issue Screen, you should have the field Time Tracking.

Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2013

Ramiro is correct. The original estimate can be set via issue create/edit screens.

If you don't set original estimate, then Tempo sets if for you when you log the first hours by calculating original estimate = remaing estimate + worked