BigPicture overriding manual entry of remaining time.

Scott Hassell August 16, 2024

Using Jira Cloud. Big Picture is overriding a manual entry of remaining hours.  For example, enter 120h ( see first screen shot).   BP will then override and put in 88H (See second screen shot).   Scheduling mode is set to Manual. Any ideas how to allow the manual entry to stick?

Capture 1.JPGCapture 2.JPG

1 answer

Suggest an answer

Log in or Sign up to answer
0 votes
Marek Duda
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 17, 2024

Check if dependencies or resource settings are messing with it. If it still changes, hit up BigPicture support.